gantt chart
1) Develop a network activity chart, and identify the critical path for a project based on the information provided in the Gantt chart below. Draw the activity network as a Gantt chart. What is the expected duration of the project?
Activity |
Expected Duration |
Predecessor |
A |
5 days |
—- |
B |
10 days |
A |
C |
8 days |
A |
D |
1 day |
A |
E |
5 days |
B, C |
F |
10 days |
D, E |
G |
14 days |
F |
H |
3 days |
G |
I |
12 days |
F |
j |
6 days |
H, I |
2) Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network.
Activity |
Duration |
Predecessors |
||||||
A |
3 |
— |
||||||
B |
5 |
A |
||||||
C |
7 |
A |
||||||
D |
3 |
B, C |
||||||
E |
5 |
B |
||||||
F |
4 |
D |
||||||
G |
2 |
C |
||||||
H |
5 |
E, F, G |
||||||
Activity |
Duration |
ES |
EF |
LS |
LF |
Slack |
||
A |
3 |
0 |
3 |
0 |
0 |
— |
||
B |
5 |
3 |
8 |
8 |
13 |
5 |
||
C |
7 |
3 |
10 |
3 |
10 |
— |
||
D |
3 |
10 |
13 |
13 |
13 |
— |
||
E |
5 |
8 |
12 |
13 |
17 |
5 |
||
F |
4 |
13 |
17 |
13 |
17 |
|||
G |
2 |
10 |
12 |
15 |
17 |
5 |
||
H |
5 |
17 |
22 |
17 |
22 |
— |